Optimizing Controls
The greatest challenge in projects with a similar configuration is in the control integration between the equipment’s manufacturer internal control and the central building automated system. Detailed specifications and coordination of the control systems integration, including specific settings integrated controllers, was the key to properly commissioning the system and achieving the expected performance.
Results
Commissioned in 2018, these measures have cut GHG emissions by over 80% and nearly eliminated the need for natural gas to heat the facility.
The diagram below represents savings to date (data was updated April 2020 to include all of 2019 savings). Higher greenhouse gas savings are anticipated once heat pump in the community centre gymnasium is in operation.
This project was featured in the Engineers and Geoscientists of BC’s 2019 spring issue of Innovation Magazine.